shopify
site analytics

24 Hr 800-377-3648

Remtech © 2019

EMERGENCY WASTEWATER TREATMENT, WASTEWATER PLANT UPGRADES & PLANT MAINTENANCE

  • Dissolve Air Floatation Pumps that operate without compressed air, pressure vessels or static mixers
  • Pump repairs and/or replacement
  • Tank, line, process cleaning and repairs
  • Tank replacement
  • Sludge dewatering systems
  • Treatment Plant Insulated Enclosures
  • Installation Chemical Feed Systems
  • WWTP Renovation design
  • Equalization Basin Design & Installation
  • Design & Installation of Environmental Monitoring Systems

  • Mobile aeration basins with micro bubble diffusers that operate with less air and power than conventional mixing systems
  • Mobile settling basins
  • Mobile dissolved air floatation systems
  • Serpentine chemical mixing/floculation systems
  • Chemical addition - acid, base, alum, polymers
  • Sludge management systems
  • Mobile flash mixers

Serving Georgia, Tennessee, Alabama, North Carolina, South Carolina, and Florida

Temporary wastewater treatment plants or emergency wastewater treatment upgrades are often required when old treatment systems fail or require upgrades to meet stricter effluent guidelines.  


Remtech provides emergency wastewater treatment systems that can be mobilized to your facility within hours to keep you facility in compliance when a new plant is being designed, constructed or simply provide an emergency or permanent upgrade to keep your facility in compliance.

Emergency Wastewater Treatment Systems

Emergency Wastewater Treatment Plant Upgrades

Remtech recently demonstrated its emergency pre-treatment facility deployment capabilities for a major food manufacturing facility when their plant began to fail with leaking tanks and non-functional pumps and a DAF system.  The temporary treatment system was designed to operate for four months while the new plant was being designed and constructed.


Six (6) 20,000 gal frac tanks were mobilized to provide unit operations for the plant.  Raw wastewater was diverted to a primary 20,000 blending tank following an existing rotating screen.  An equalization basin was constructed of three (3) frac tanks connected in parallel where the flow was spit equally between the three tanks providing a five hour retention time for flow and concentration equalization.  


Mixing was provided in each tank by constructing a fine bubble (50 micron) diffusion system assembled outside each tank that was anchored in each tank by eight (8) 85 pound magnets. Pre-assembled air diffuser heads and feed lines were inserted through a 30" manhole with only 5 universal fittings requiring tightening inside each frac tank.  Sixteen (16) diffusers in each tank provided concentration equalization and enough mixing to prevent settling of solids.  An existing 5 Hp rotary lobe blower (187 cfm @ 15 psi) provided air that was balanced between the three tanks to provide uniform mixing and oxygen for biological oxidization.  Air mixing pilot tests on Remtech’s four diffuser heads on 34” centers required 1.3 cfm air per head at 5 psi to produce a radius of influence of 8 ft.  Available air provided three times the air required for mixing and oxidization.


Wastewater from the equalization basin flowed through a seven (7) tier 10 ft long serpentine chemical floculation/mixing system constructed out of four-inch schedule 80 PVC that provided a 15 second mixing time between acid/base/alum addition and a PID pH controller.  A new 20 micron bubble pump was installed to restore the operation of the dissolved air floatation system. This pump eliminated the need for a compressor, pressure vessel, ejector, and static mixer.


The plant was constructed in phases that allowed the plant to continue to operate and was completed in 15 days.

Wastewater Treatment Plant Maintenance

  • Lift Station Cleaning
  • Tank Cleaning
  • Sludge Removal
  • Filter Media Replacement
  • Grit Chamber Cleaning
  • Aeration System Installation & Repair