24 Hr Emergency Response

800-377-3648

Remtech Engineers Logo

10,000 Environmental Remediations Since 1975

Remtech © 2024

| CAREERS |

PROBLEM


Remtech constructed an 60,000 gpd emergency frac tank pre-treatment facility for a major food manufacturing facility when their plant failed with leaking tanks, non-functional pumps and neutralization system, and a DAF air injection system that stopped working. Regulatory authorities required that manufacturing stop until a waste treatment system was operational.


SOLUTION


The temporary treatment system was brought on line in three days and completed in 15 days and was designed to operate for four months (but continued for 9 months) until the permanent plant was completed.


Six (6) 20,000 gal frac tanks were mobilized to provide unit operations for the plant.  Raw wastewater was diverted to an primary 20,000 blending and solids screening tank.  A 60,000 gal equalization basin was constructed of three (3) 20,000 gal. frac tanks connected in parallel. Flow between tanks was spit equally providing a five hour retention time for flow and concentration equalization. Remtech's magnetic aeration system (Patent Pending) consisting of Fifty (50) micron air diffuser manifolded heads were inserted through 20" manholes with connections consisting of 5 universal fittings and 85 pound anchoring magnets.  Sixteen (16) diffusers in each tank provided flow and concentration equalization and enough mixing to prevent settling of solids.  An existing 5 Hp rotary lobe blower (187 cfm @ 15 psi) provided excess air to provide uniform mixing and oxygen for biological oxidization. See Remtech Magnetic Aeration System


Air mixing pilot tests on four diffuser heads on 34” centers required 1.3 cfm air per head at 5 psi to produce a radius of influence of 8 ft in each tank.  Available air provided three times the air required for mixing and oxidization.  Wastewater from the equalization basin flowed through a seven (7) tier 10 ft long serpentine chemical floculation/neutralization/ mixing system constructed out of four-inch schedule 80 PVC that provided a 15 second contact/mixing time for acid/base/alum addition.


Chemical addition was controlled by a PID pH controller.  A new 20 micron bubble pump was installed to restore operation of the dissolved air floatation system that replaced the old compress air injection system. This pump replaced the existing compressor, pressure vessel, ejector, and static mixer.


COST/BENEFITS


This temporary wastewater treatment system allowed this manufacturing facility to continue to manufacture productand avoid a costly shut down period.

Stormsewer Fuel Infiltration Point Located with CCTV Camera
Pipeline located by Potholing and Collection of Overburden in Vac Box

Serpentine Chemical Mixing System Fabricated in One Day for Acid, Base and Alum Addition

Location: Atlanta, Georgia

Client: Confidential Food Manufacturing Facility

Contract Amount: $430,000

Emergency Frac Tank 60,000 gal Aerated Equalization Basin

with Micro Bubble Diffusion

Emergency Bypass Frac Tank Wastewater Treatment Facility | Atlanta, GA

20 Micron Bubble Dissolved Air Floatation Pump

Installed that Operates without Compressed Air

or Pressure Tank Increased Solids

Removal Efficiency

Frac Tank Aeration System with 12-50 Micron Diffuser Heads

(Offset Diffusers Creates Circular Mixing Pattern)