Division of SET Environmental
10,000 Environmental Remediations Since 1975
24 Hr Emergency Response
800-377-3648
| Contact Us | Careers | Employees
- HOME
- About Us
- Services
- Environmental Remediation Services
- Remediation Engineering Contracting
- Emergency Spill Response & Cleanup
- Disaster Response
- Industrial Vacuum Truck & Emergency Recovery Services
- Tank Cleaning & Industrial Services
- Waste Management & Disposal
- Mobile Wastewater & Remediation Systems
- Stormwater Basin Management & Inspections
- Environmental Engineering Services
- Groundwater & Soil Remediation
- Asbestos & Mold Remediation
- Mercury Remediation
- Chemical Fixation & Solidification
- Combustible Dust Cleanup & Hazard Analysis
- Metal Dust Cleaning & Hazard Analysis
- Homeless Encampment Cleanups
- PFAS Treatment Systems
- Lead Paint Abatement
- OSHA and EPA Training
- Sewer Jetting VACUJET and Inspection Services
- Spill Prevention & Secondary Containment
- Loading Rack Fall Protection, Walkways & Catwalks
- Renewable Energy Engineering
- Demolition & Site Restoration
- Bioremediation
- Bioremediation Optimization Primer
- Biopile Optimization Primer
- Bioremediation Accelerator HC-2000
- Bioremediation White Paper
- Bioremediation Degradation Curves
- Bioremediation Efficacy Testing
- Biorediation Toxicity Testing
- Diesel Bioremediation with Dual Phase Extraction
- Bioremedation of River Bank Jet Fuel
- Bioremediation of Gasoline in Wetland
- Biosparge of Solvent Site
- Bioremediation of Airport Jet Fuel Spill
- Detention Pond Diesel Bioremediation
- Bioremediation of Diesel on Mainline Track
- Bioremediation of Diesel Track Collision Site
- Bioremediation At-Grade Collison Site
- Bioremediation of Waste Oil
- Bioremediation of Transformer Oil
- Industries Served
- Case Histories
- Temporary Food Wastewater Treatment Plant
- Landfill Leachate Treatment Plant Design
- Diesel Fuel Dual Phase Extraction
- Gasoline Remediation in Fractured Rock
- Chlordane Superfund Site Remediation
- Agricultural Chemical Fire Response and Remediation
- PFAS Mobile Treatment Systems
- PFAS Treatment at Chemical Plant Fire
- Leaking Fuel Pipeline Remediation
- Spill Prevention at Railyards
- Railcar Loading RacK Design
- Leaking Chlorine Railcar Capped
- Chlorine Dioxide Explosion Remediation
- Vacujet Heavy Solids Sewer Cleaning
- Clemical Plant Fire Response and Remediation
- Train Fire Investigation
- Arsenic Building Site Remediation
- Chemical Fixation of Carpet Latex Sludge
- Power Center Fuel Remediation
- Power Plant Transformer Fire Remediation
- Transformer Explosion Remediation
- Mercury Hydroelectric Plant Remediation
- Decontamination of Abandoned Hospital
- Toluene Diisocyanate Remediation
- Loading RacK Tanker Unloading Design
- UST Tank Failure Investigation
- Gasoline Tanker Fire Emergency Response
- Publications
- TREATMENT & EQUIPMENT SALES
Railcar Unloading Rack Design with Secondary Containment
Location: Atlanta, Georgia
Client: Major Petroleum Company
Contract Amount: Confidential

Railcar Ethanol Unloading Rack Design & Construction Management

Completed Railcar Ethanol Unloding Rack with Secondary Containment
RAILCAR ETHANOL UNLOADING RACK PROBLEM
A major petroleum company retained Remtech Engineers to obtain building permits and provide construction management or a new ethanol railcar unloading rack at a petroleum terminal.
ETHANOL RAILCAR UNLADING RACK SOLUTION
➤ Remtech provided unloading rack siting, grounding review, fire detection/suppression review, submission of building permit drawings, and construction management services for this project.
➤ Remtech reviewed footing designs and integration of the unloading rack spill diversion routing into the plant’s existing AST tank farm’s secondary containment and treatment system.
➤ Building and fire prevention permits were obtained for construction of this facility.
ETHANOL RAILCAR UNLOADING RACK DESIGN COST/BENEFITS
This project was completed on schedule and budget. The contractor was held responsible for removing and reinstalling inadequate rack footings caught by Remtech.