Division of SET Environmental
10,000 Environmental Remediations Since 1975
24 Hr Emergency Response
800-377-3648
| Contact Us | Careers | Employees
- HOME
- About Us
- Services
- Environmental Remediation Services
- Remediation Engineering Contracting
- Emergency Spill Response & Cleanup
- Disaster Response
- Industrial Vacuum Truck & Emergency Recovery Services
- Tank Cleaning & Industrial Services
- Waste Management & Disposal
- Mobile Wastewater & Remediation Systems
- Stormwater Basin Management & Inspections
- Environmental Engineering Services
- Groundwater & Soil Remediation
- Asbestos & Mold Remediation
- Mercury Remediation
- Chemical Fixation & Solidification
- Combustible Dust Cleanup & Hazard Analysis
- Metal Dust Cleaning & Hazard Analysis
- Homeless Encampment Cleanups
- PFAS Treatment Systems
- Lead Paint Abatement
- OSHA and EPA Training
- Sewer Jetting VACUJET and Inspection Services
- Spill Prevention & Secondary Containment
- Loading Rack Fall Protection, Walkways & Catwalks
- Renewable Energy Engineering
- Demolition & Site Restoration
- Bioremediation
- Bioremediation Optimization Primer
- Biopile Optimization Primer
- Bioremediation Accelerator HC-2000
- Bioremediation White Paper
- Bioremediation Degradation Curves
- Bioremediation Efficacy Testing
- Biorediation Toxicity Testing
- Diesel Bioremediation with Dual Phase Extraction
- Bioremedation of River Bank Jet Fuel
- Bioremediation of Gasoline in Wetland
- Biosparge of Solvent Site
- Bioremediation of Airport Jet Fuel Spill
- Detention Pond Diesel Bioremediation
- Bioremediation of Diesel on Mainline Track
- Bioremediation of Diesel Track Collision Site
- Bioremediation At-Grade Collison Site
- Bioremediation of Waste Oil
- Bioremediation of Transformer Oil
- Industries Served
- Case Histories
- Temporary Food Wastewater Treatment Plant
- Landfill Leachate Treatment Plant Design
- Diesel Fuel Dual Phase Extraction
- Gasoline Remediation in Fractured Rock
- Chlordane Superfund Site Remediation
- Agricultural Chemical Fire Response and Remediation
- PFAS Mobile Treatment Systems
- PFAS Treatment at Chemical Plant Fire
- Leaking Fuel Pipeline Remediation
- Spill Prevention at Railyards
- Railcar Loading RacK Design
- Leaking Chlorine Railcar Capped
- Chlorine Dioxide Explosion Remediation
- Vacujet Heavy Solids Sewer Cleaning
- Clemical Plant Fire Response and Remediation
- Train Fire Investigation
- Arsenic Building Site Remediation
- Chemical Fixation of Carpet Latex Sludge
- Power Center Fuel Remediation
- Power Plant Transformer Fire Remediation
- Transformer Explosion Remediation
- Mercury Hydroelectric Plant Remediation
- Decontamination of Abandoned Hospital
- Toluene Diisocyanate Remediation
- Loading RacK Tanker Unloading Design
- UST Tank Failure Investigation
- Gasoline Tanker Fire Emergency Response
- Publications
- TREATMENT & EQUIPMENT SALES
Landfill Leachate Superfund Treatment Plant Design | Central, AL
Location: Central Alabama
Client: Major Chemical Company
Contract Amount: $170,000

Superfund Landfill Leachate Treatment Plant Design
LANDFILL LEACHATE TREATMENT PLANT PROBLEM
Remtech Engineers was engaged by the corporate environmental engineering department of a Fortune 100 Energy Corporation to design a groundwater treatment plant for leachate generated from a chemical waste landfill at an Alabama Superfund site to operate under flood conditions.
GROUNDWATER TREATMENT AT SUPERFUND SITE SOLUTION
A waste impoundment was closed by constructing an engineered storage facility. Bentonite slurry walls were constructed and solidification agents were introduced to stabilize wastes. Gas vents, and a High Density Polyethylene Liner was installed to prevent surface water infiltration. A cap was constructed over the landfill.
An estimated three-foot water depth frequently covered the site due to the Corps of Engineers altering spillway elevations at dams located up and downstream. PVC extraction wells were installed in the cap and drilled inside and outside of the slurry wall to intercept and treat leachates from the landfill and direct clean upgradient groundwater around the storage facility.
Submersible pumps were placed in the bottom of each well to produce extraction rates of 50 gpm. North and south galleries were connected to control panels to facilitate operation of single or multiple pumps. The collection gallery initially drained into an existing onsite concrete retention basin.
Remtech evaluated alternative functional designs and prepared detailed plans, specifications, material takeoffs, and contract/bid documents in a 60-day period. This plant was constructed 8-months later. Remtech Engineers also trained plant operations personnel.
GROUNDWATER TREATMENT AT SUPERFUND SITE COST/BENEFITS
Unit operation carbon and stainless steel tanks, quartz lighting, and safety railing were salvaged from the client’s onsite abandoned phenoxy plant. An existing concrete retention basin was used as a foundation and secondary containment structure for the plant. Unique Remtech plant design features including floating weirs, saved the client over $110,000 thousand dollars.