Project Owner: Major News Publication Facility
Location: Athens, Georgia
Contract Value: $270,000
Problem
- Construction Stopped for 4 Months
- Free Product Under 70,000 sf Building Foundation
- Geology - Fractured Rock (Granite Schist)
- Remedial Plan to Obtain Building Permits from State Fire
Marshal
- Perform Remediation Concurrent with Construction
Approach
- Mobilized Portable Treatment Plant
- Demonstrated Hydraulic Connectivity & Manageable
Free Product Removal
- Remediation Initiated During Construction (Soil Vapor
Extraction/Ventilation)
- Designed Remedial System & Coordinated Installation
with Building Construction
- Located Source & Determined Source Stopped
- Secured Building & Occupancy Permits from State Fire
Marshal
Project Benefits
- $16 Million Building Completed
- Mobile Groundwater Treatment Facility Used in Final Design
- Developed Technical Data Base for Responsible Party Cost
Recovery
- Remediated 600 cy of Soils Onsite
- Free Product Removed after 2 Years of Operation
- No Vapors Detected Under Building
|
|

Publication Facility with Treatment Plant

Contamination in Fractured Rock

Remtech Twin Stripping Towers

BioVent & Ventilation System |